Two months after repeated service issues arose on Ottawa’s Confederation Line , the city says the number of incidents disrupting light-rail (LRT) service is on the decline, but the head of the public transit agency still can’t say when train service will be stable.

“I don’t have that answer for you, councillor,” OC Transpo boss John Manconi said when asked by Coun. Jeff Leiper on Tuesday when the persistent LRT issues will be fixed.

The City of Ottawa’s finance and economic development committee received an update on the LRT’s performance at city hall, a month after councillors learned that plaguing train service since early October are the train doors, two computers and the rail switches.

The number of incidents causing LRT disruptions – particularly during the morning and afternoon rush hours – has been “trending downwards” since then, Manconi told councillors on Tuesday.

But, he said, stabilizing the $2.1-billion LRT line largely depends on diagnosing the root cause of the issues with the train control and monitoring system (TCMS) – one of the two computers that has been referred to as “the brain of the train.”

Politicians, media ride LRT trains ahead of Confederation Line’s handover to city

Politicians, media ride LRT trains ahead of Confederation Line’s handover to city

Speaking with reporters after his presentation, Manconi said the consortium hired to build and maintain the east-west Confederation Line, Rideau Transit Group (RTG), hasn’t yet given OC Transpo a date for when train service will be stable.

“When I ask someone for a date, if they can’t guarantee that date, then I don’t want to hear about it. I want to see the evidence to demonstrate to me they can achieve that date,” he said.

“I had a very frank discussion with their entire executive committee yesterday with the city manager. And I asked: ‘Do you have a firm date as to when you can fix the TCMS by? And the answer was: ‘No, we do not.’ They wish they do.”

Asked about the lack of an end date, Mayor Jim Watson suggested it’s more important to focus on finding permanent solutions, instead of a “quick fix,” because the LRT is “a complex system.”

“What we have to do is get it right and make sure we get it right, not just for two or three days and celebrate, but make sure it’s several weeks on end,” the mayor told reporters.

The train fleet now has software that minimizes the impact of those computer problems and collects “critical” data for train engineers, he said. OC Transpo has also made some operational changes that have helped crews reset the system faster when issues arise, according to Manconi.

Trending Stories

Popular Videos

As for the door issues, those are subsiding too, but the train cars aren’t to blame for all those incidents, Manconi said. Three train service delays last week were “a direct result of customers forcing open or prying open the doors,” he told councillors.

“The customers need to leave the doors alone,” he underscored.

Some rail switch issues continue and OC Transpo has asked RTG’s maintenance arm, Rideau Transit Maintenance (RTM) to have more staff monitoring the switches at Tunney’s Pasture and Blair stations during peak periods and during bad weather. In general, RTM has “significantly increased resources on the ground” to deal with train issues.

“I will give credit when credit is due,” Manconi told councillors. “That’s a very positive sign and they’re definitely listening to us.”

After due to freezing rain, Watson asked Manconi what OC Transpo is doing to ensure that doesn’t happen on the Confederation Line, given Ottawa’s train also has overhead wires.

Manconi said the city has a “winter plan” for different weather conditions and, in icy conditions, OC Transpo would continue to run “limited service” end-to-end “to eliminate ice build-up on the overhead catenary system.”

The city’s position is that RTG “has not fulfilled the contractual obligations” for maintaining the Confederation Line, councillors heard Tuesday.

In response to what it claims is “consistently poor performance” by RTG, the city plans to immediately begin “an operational review” of RTG and RTM’s work and expand its oversight of train car maintenance to all maintenance activities along the line, in order to address issues, gaps and concerns.
Read more on globalnews.ca
News Topics :
Similar Articles :
Canada
A+ Top city officials doled out apologies on Wednesday for Ottawa’s problem plagued light rail transit LRT system, but the head of OC Transpo could not provide timelines for when the biggest...
Canada
Mayor Jim Watson and councillors received an update on the status of the delayed Confederation LRT line on Tuesday, one day before Ottawa city council is expected to vote on...
Canada
The builder of Ottawa’s thrice delayed light rail train says it has finished construction and testing of the system and has applied for “substantial completion” of the $2.1 billion project, according to the...
Canada
+ For the second time in about three months, the consortium building the first stage of Ottawa’s Confederation LRT line has applied to move on to a critical 12 day trial...
Canada
Transit Commission chair Allan Hubley tries out the LRT simulator. Ottawa councillors and staff were invited to check out the OC Transpo facility on Monday including the command and training...